Vietnam Veterans Memorial
As-Built Survey

Every one of 2,946 engraved bricks had to come up. Every one had to go back exactly where it was.

Location: Veterans Park, Milwaukee, WI  ·  Client: Avalon Investments Group Inc.  ·  Services: Site Control · Low-Altitude UAS Photogrammetry · Orthomosaic · Point Cloud · Grid Elevations · As-Built Documentation · Construction Staking & Layout

The Southeastern Wisconsin Vietnam Veterans Memorial was being rebuilt from the ground up - new base, new walks, and every paver lifted. Lynch documented the memorial exactly as it stood, at a resolution fine enough to read weathered engraving, then returned to stake the geometry for the rebuild - so the contractor could put all 2,946 bricks back in their original positions.

A Survey Where Position Was Not the Only Thing That Mattered

Dedicated in 1991, the memorial sits on reclaimed lakefront ground in Milwaukee's Veterans Park. Three granite columns stand for those killed in action, those held as prisoners or still missing, and those who came home. Below them, a fan of engraved bricks carries the names - rank, branch and date - of the people the memorial exists for.

After thirty-five years the ground had settled and buckled, and the pavers had eroded. The fix was a full rebuild: lift the entire brick field, lay a new base, and reinstall. That created an unusual survey problem. A normal as-built records where things are. Here, the record also had to be legible, because some of the engraving had worn past the point where a person standing over it could read the name.

Working for Craig T. Ellsworth, Architect, of Avalon Investments Group Inc., who administered the project for the hardscape contractor, Lynch was asked to field-measure the pavers, paving, benches and structures as they stood - and to take elevations on a grid, so any drainage problem could be found before the bricks went back down rather than after.

Aerial orthophoto of the Southeastern Wisconsin Vietnam Veterans Memorial showing the oval plaza, the fan-shaped brick field, radial walkways and perimeter benches

Four Feet Off the Ground, Flown by Hand

The work began with control. Six points were set around the memorial and tied to each other within 0.01 of a foot, giving every later measurement something to check against.

The capture itself had to be flown manually. Mapping software will not collect data at the altitude this job needed - roughly four feet above the pavers - so our FAA-certificated remote pilot, Sr. Survey Crew Chief Seth Oldenburg, flew a three-foot grid across the entire site by hand, passing over every brick from several angles. That produced thousands of photographs, each geolocated with RTK GPS.

Photogrammetry assembled those images into a dense point cloud and a single orthomosaic, which was then crosschecked back against the conventional survey and the site control to confirm it held survey-grade accuracy across the whole site - not just in the middle, where photogrammetry always looks good.

Orthophoto detail of engraved memorial bricks showing names, rank, service branch and date legible at survey grade

What We Delivered

0.0013 ft Per Pixel

An orthomosaic at roughly four tenths of a millimeter per pixel, in NAD83(2011) Wisconsin South and NAVD88 - fine enough to read engraving the eye could no longer make out.

Survey-Grade Control

Six control points around the site tied within 0.01 of a foot, with the photogrammetry crosschecked back against conventional survey.

Reinstallation Record

Position documentation for all 2,946 bricks plus the benches, walks and structures, so the field could be rebuilt in its original arrangement.

Construction Staking & Layout

Curve geometry set out on the ground for the rebuild - radius points, semi-circle midpoints and two-foot offsets at finished grade.

Grid Elevations

Elevations on a grid across the memorial, so drainage could be assessed before reinstallation instead of discovered afterwards.

Close detail from the orthophoto: individual engraved bricks with POW/MIA emblems, names, rank and date, with aggregate and grass visible in the joints

Detail from the orthophoto. This is not a ground photograph - it is the aerial survey product, at the resolution that let worn engraving be read and transcribed.

Then Back in September, to Stake It

Recording the memorial was only half the job. Once the base was in, the geometry had to be set out again on the ground - and the memorial is almost entirely curves. The plaza is an oval, the brick field is a fan, and the walks are arcs struck from radius points. Curves are the one thing a crew cannot rebuild by eye.

In September our crew returned to stake the layout: radius points, semi-circle midpoints, and offsets held two feet clear of tangent and radius so the stakes survived the work going on around them, all at finished grade. That is what let the contractor rebuild the arcs true to the shape the July survey had recorded, rather than approximately.

Rebuilt, and Back Where It Belonged

Removal began in July 2026. The memorial was rebuilt on a new base with new walks, and all 2,946 bricks were reset - in the layout the survey recorded, with the names intact. It was rededicated on Veterans Day 2026.

Lynch's part was the survey and the layout. The credit for the restoration belongs to the War Memorial Center, who raised the money and ran the project, and to Pat Connerton of Pro Hardscape & Lawn and the crews who did the physical work. What the survey contributed was certainty: that the field going back down matched the field that came up, and that no name was lost in between.